Secondary school in Ilyichevsky district of Mariupol

Year of construction: 1966

Contract organization: LLC "MSK-Garant""

Damages: The roof, offices of the first and third floors, windows and doors were destroyed by direct shelling.

Works performed: overhaul of the roof and damaged structure. Engineering communications were carried out, doors and windows were replaced. Interior fit-out works and restoration of facades were performed. The school area was improved: a gazebo was installed, exercise equipment was installed, a new football field was made with a special coating 

object before repair-
restoration work

Secondary school in Ilyichevsky district of Mariupol
Secondary school in Ilyichevsky district of Mariupol
Secondary school in Ilyichevsky district of Mariupol

object after repair-
restoration work

Secondary school in Ilyichevsky district of Mariupol
Secondary school in Ilyichevsky district of Mariupol
Secondary school in Ilyichevsky district of Mariupol
Secondary school in Ilyichevsky district of Mariupol