Construction and installation department of RKS-NR LLC is restoring a gymnasium in Mariupol
Specialists of the Construction and Installation Department of RKS-NR LLC are restoring the gymnasium building in the Ilyichevsky district of Mariupol.
Year of construction - 1953, total area - 2,687 m2. The educational institution is designed for 300 places.
During the hostilities, the building was not seriously damaged, but due to the long-term lack of necessary maintenance and repairs, at the time the work began, it was already in disrepair. To date, the dismantling work of the first, second floors and roof has been completely completed.
Builders are performing interior finishing work and plastering the first floor, and installing partitions. Floors in basements are being dismantled.
With the coordination of the Ministry of Construction of Russia, SMU RKS-NR LLC is restoring 12 social facilities in Mariupol.